OPEN HOUSE FOR Road Widening and Rehabilitation of 14400 S and 2200 W

open house

Open House on Thursday, January 4, 2018 6-8 PM at City Hall

to discuss park strip landscaping options: rock, mulch, or grass (only supplied with owner provided irrigation)


Road Widening and Rehabilitation Project (14400 S and 2200 W)

14400 S is being widened, along with constructing a traffic circle at 2200 W.  This will improve the flow of traffic and create sidewalk facilities to provide a safe walking environment for students. 2200 W is being rehabilitated, meaning structurally repaired with the surface reconditioned and drainage improved so the road will be smoother and safer.


Where the construction will be.

14400 S from Redwood Road to 2200 West

2200 West from 13800 S to 15000 S


Timeline for the construction.

Bid awarded in January

Construction to start February. Construction will done in stages with an estimated one year completion.


The street will be dug up and then reconstructed with new road base and surface placed.

Storm drains will be constructed/reconstructed to accommodate drainage requirements.

Utility work will involve moving power poles, installing new water lines and water services.


There will be some disruption during construction including: traffic detours and/or delays, broken pavement and temporary water shut-offs. Construction may necessitate some resident owned fencing removal which will be considered for replacement in kind.

Facebook Twitter Google Plus Email

Other News in Home

point of the mountain

Point of the Mountain Vision Survey

Posted on: December 5, 2017
dog

Dog Park Citizens Committee

Posted on: December 5, 2017