Projects In Bluffdale

Water Projects





Transportation and Street Projects

  • 13800 Rotomill and Overlay Project between 2950 West and 3600 West has been sent out to bid. This is a cost-shared project with Riverton, with both cities paying their share based on city boundaries. Construction is scheduled to begin August 10th.
  • 14400 S Road Improvement Project (including roundabout): Road improvement and widening project including roundabout, sidewalk, curb and gutter on 14400 South from Redwood Road to 2200 West. The City is currently completing the bid package which is scheduled to be advertised mid to late August.
  • Porter Rockwell Blvd. (PRB) Project There are 5 planned segments. Segments 1, 2 and 3 are completed. The ribbon cutting for segment 3 was on Wednesday, July 26th. See maps for project details.
PRB Overall Segments Exhibit
PRB Ribbon Cutting

Storm Drain Projects



Parks Projects

The construction for Vintage Park (located at approximately 14100 Loumis Parkway) will begin in August. This 5 ½ acre park will have a pavilion, picnic shelters, gazebo, splash pad, playground, a volleyball court, tennis and pickle ball courts. The construction is scheduled to take about 7 months.

Vintage Park drawing

Street Lights


Other Projects

  • Jordan School District has purchased property and is planning schools on the east side of the City to accommodate future growth.
  • LED Message Monument Sign at City Hall:
    The foundation for the sign is now complete. The assembly of the sign is scheduled to begin this week. The construction should take two to three weeks.

​14600 South Construction Trestle Area


Sunday, June 11, 2017 a contractor (Beck Construction) working for UDOT rebuilt a portion of 14600 South. This was next to the rail road bridge (trestle) where faults/deep creeps had developed in the asphalt along a portion of the road next to the steep embankment that is over 4 homes in Springview Farms.

The contractor excavated at least 5 feet of road uncovering a bit of history as defined by the layers of pavement that were uncovered. The excavation was not as deep as the flowline of the Salt Lake City Canal that is on the east side on the road. The contractor uncovered several layers of pavement including a concrete slab, base course and an old asphalt concrete surface that was disintegrating at the bottom of the five foot excavation. The asphalt concrete could have been placed in the late 1800s or early 1900s.

The material excavated had some moisture but not sufficient to cause concern. The contractor repaired the road by placing a layer of cobble rocks of various depth (2ft-5ft) of 4-inch minus rocks covered by geotextile fabric covered by 8-inch of untreated base and eventual new 6-inch of asphalt pavement.

The patch extended for 40 feet from about the center of the road to the edge. This is a temporary fix to provide better protection. UDOT and the City plan on meeting to discuss the possible options for better studying the area and provide a permanent solution.